PK0-004 · Question #908
A vendor contacts the project manager regarding a particular component. The original scoped materials are no longer available, but the vendor has a replacement that can be used. Which of the…
The correct answer is A. Resources. When a replacement material substitutes for an originally scoped component, the primary impact is on resources, since the material itself is a project resource.
Question
A vendor contacts the project manager regarding a particular component. The original scoped materials are no longer available, but the vendor has a replacement that can be used. Which of the following will MOST likely be impacted with the replacement material?
Options
- AResources
- BEnvironment
- CScope
- DTimeline
How the community answered
(24 responses)- A83% (20)
- B4% (1)
- C8% (2)
- D4% (1)
Why each option
When a replacement material substitutes for an originally scoped component, the primary impact is on resources, since the material itself is a project resource.
In project management, resources include people, equipment, and materials. Substituting one vendor component for another directly changes the material resource being used, potentially requiring re-evaluation of specifications, compatibility, and procurement. The resource plan and resource assignments related to that component must be updated.
The environment refers to the physical or organizational setting in which the project operates, which is not directly affected by a material substitution.
Scope defines what the project will deliver, and a compatible replacement material fulfills the same functional requirement without changing the project's scope.
Timeline could be secondarily affected, but the primary and most direct impact of a material change is on the resource being used, not the schedule.
Concept tested: Impact analysis of material substitution on project resources