PK0-004 · Question #89

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the project…

The correct answer is C. Withdrawing. Avoiding, also known as "withdrawing," postpones the issue until the project manager can be better prepared or other parties can resolve the issue. This technique often involves sidestepping

Project management concepts

Question

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the project manager using?

Options

  • ACompromising
  • BSmoothing
  • CWithdrawing
  • DAccepting

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    90% (28)

Explanation

Avoiding, also known as "withdrawing," postpones the issue until the project manager can be better prepared or other parties can resolve the issue. This technique often involves sidestepping

Topics

#conflict resolution#withdrawing technique#team management