CompTIA
PK0-004 · Question #89
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the project…
The correct answer is C. Withdrawing. Avoiding, also known as "withdrawing," postpones the issue until the project manager can be better prepared or other parties can resolve the issue. This technique often involves sidestepping
Project management concepts
Question
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the project manager using?
Options
- ACompromising
- BSmoothing
- CWithdrawing
- DAccepting
How the community answered
(31 responses)- A3% (1)
- B6% (2)
- C90% (28)
Explanation
Avoiding, also known as "withdrawing," postpones the issue until the project manager can be better prepared or other parties can resolve the issue. This technique often involves sidestepping
Topics
#conflict resolution#withdrawing technique#team management