The correct answer is C: Withdrawing. Avoiding, also known as "withdrawing," postpones the issue until the project manager can be better prepared or other parties can resolve the issue. This technique often involves sidestepping
Question
Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the project manager using?
Options
- ACompromising
- BSmoothing
- CWithdrawing
- DAccepting
Explanation
Avoiding, also known as "withdrawing," postpones the issue until the project manager can be better prepared or other parties can resolve the issue. This technique often involves sidestepping