A large number of issues and feature requests are brought to the project manager's attention during a go-live. Which of the following should the project manager do FIRST?

The correct answer is B. Log each issue or request. If all the issues are taken into consideration at the same time, it is likely that some of them also being important may go unnoticed. So it is better to log each issue or request.

Project management concepts

Question

A large number of issues and feature requests are brought to the project manager's attention during a go-live. Which of the following should the project manager do FIRST?

Options

  • AInform the change control board.
  • BLog each issue or request.
  • CAsk for approval from the sponsor.
  • DHold an impromptu review meeting.

How the community answered

(33 responses)
  • B
    91% (30)
  • C
    3% (1)
  • D
    6% (2)

Explanation

If all the issues are taken into consideration at the same time, it is likely that some of them also being important may go unnoticed. So it is better to log each issue or request.

Topics

#issue management#go-live#issue log#change control

Community Discussion