A company's finance director asks the PMO for help gathering a group of specialists to work in an operations center. Which of the following is the MOST likely action the PMO will take?

The correct answer is B. Assign a project manager to start working on the project charter. Assigning a project manager to start working on the project charter (B) is correct because the request - gathering a group of specialists to staff an operations center - represents a new initiative requiring formal project initiation. The project charter is the first formal…

Project management concepts

Question

A company's finance director asks the PMO for help gathering a group of specialists to work in an operations center. Which of the following is the MOST likely action the PMO will take?

Options

  • ARequest funding to hire the group of specialists.
  • BAssign a project manager to start working on the project charter.
  • CAsk the finance director to sign the statement of work.
  • DInform the finance director the PMO only works for projects.

How the community answered

(39 responses)
  • A
    3% (1)
  • B
    79% (31)
  • C
    10% (4)
  • D
    8% (3)

Explanation

Assigning a project manager to start working on the project charter (B) is correct because the request - gathering a group of specialists to staff an operations center - represents a new initiative requiring formal project initiation. The project charter is the first formal document that authorizes a project and gives the project manager the authority to apply resources. Even if the end state is operational in nature, standing it up requires a project. Requesting funding independently (A) is not the PMO's role without first initiating the project. Asking the director to sign a statement of work (C) skips the initiation phase and is premature. Informing the director that the PMO only works on projects (D) is incorrect; the request is, in fact, project work (building an operations center).

Topics

#PMO#project initiation#project charter#organizational roles