The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.
The correct answer is A. -80,000. 20,000 - 100,000 = -80,000
Project management concepts
Question
The design activity of a project has the following cost attributes:
PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.
Options
- A-80,000
- B-70,000
- C10,000
- D120,000
How the community answered
(36 responses)- A81% (29)
- B11% (4)
- C3% (1)
- D6% (2)
Explanation
20,000 - 100,000 = -80,000