A functional manager within a project is requesting to edit the display features of an application that is being developed. Which of the following has the authority to approve the edit?

The correct answer is A. PM. The project manager has authority over project deliverables during project execution, including minor changes to features such as display modifications. The CCB (Change Control Board) handles formal, significant change requests that impact approved scope, schedule, or cost…

Project management concepts

Question

A functional manager within a project is requesting to edit the display features of an application that is being developed. Which of the following has the authority to approve the edit?

Options

  • APM
  • BCCB
  • CPMO
  • DSME

How the community answered

(59 responses)
  • A
    90% (53)
  • B
    2% (1)
  • C
    7% (4)
  • D
    2% (1)

Explanation

The project manager has authority over project deliverables during project execution, including minor changes to features such as display modifications. The CCB (Change Control Board) handles formal, significant change requests that impact approved scope, schedule, or cost baselines. A cosmetic display-feature edit requested through normal channels falls within the PM's authority to evaluate and approve without escalating to the CCB. The PMO (C) provides governance and support but does not approve individual deliverable changes. The SME (D) advises but has no approval authority.

Topics

#change authority#PM authority#change management#project governance