A manager is reviewing some projects with two project managers who are working on the financial system. Which of the following BEST describes this type of review?
The correct answer is C. Portfolio. Portfolio collection of projects, programs, and operational work to achieve the strategic business objectives of an organization.
Project management concepts
Question
A manager is reviewing some projects with two project managers who are working on the financial system. Which of the following BEST describes this type of review?
Options
- AOperations
- BProject
- CPortfolio
- DProgram
How the community answered
(26 responses)- A8% (2)
- B4% (1)
- C88% (23)
Explanation
Portfolio collection of projects, programs, and operational work to achieve the strategic business objectives of an organization.