A project team has determined it will need to source data from a system that was not part of the project scope. The role of the project manager is to analyze which of the following impacts?

The correct answer is D. Schedule, budget, and quality. PMs are always concerned about constraints and balance. They know the scope will change so they need to balance it out with the remaining 3. Time, Budget, Quality.

Project management concepts

Question

A project team has determined it will need to source data from a system that was not part of the project scope. The role of the project manager is to analyze which of the following impacts?

Options

  • ATechnical design, schedule, and budget
  • BBusiness process impacts and resourcing
  • CNew software and hardware requirements
  • DSchedule, budget, and quality

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    13% (7)
  • C
    7% (4)
  • D
    76% (41)

Explanation

PMs are always concerned about constraints and balance. They know the scope will change so they need to balance it out with the remaining 3. Time, Budget, Quality.

Topics

#impact analysis#scope change#schedule and budget#quality impact