PK0-004 · Question #561

Team members in a projectized organization are released at the end of a project and placed on the "bench". Which of the following should the benched team members do NEXT?

The correct answer is C. Report to the project manager. In projectized organizations, the PM calls the shots. The resources work for the PM. These resources belong to the PM's project alone and has authority. A drawback is that the team needs to know "what next" at the end of the project. This can cause a little anxiety for my team.

Project management concepts

Question

Team members in a projectized organization are released at the end of a project and placed on the "bench". Which of the following should the benched team members do NEXT?

Options

  • AFind a new project.
  • BCheck in with a functional manager.
  • CReport to the project manager.
  • DContact the project sponsor.

How the community answered

(56 responses)
  • A
    2% (1)
  • B
    2% (1)
  • C
    91% (51)
  • D
    5% (3)

Explanation

In projectized organizations, the PM calls the shots. The resources work for the PM. These resources belong to the PM's project alone and has authority. A drawback is that the team needs to know "what next" at the end of the project. This can cause a little anxiety for my team.

Topics

#projectized organization#organizational structure#team management#resource release