PK0-004 · Question #482

PK0-004 Question #482: Real Exam Question with Answer & Explanation

The correct answer is B: Business continuity response. A business continuity response is the appropriate communication type when a major disruptive event-such as a natural disaster destroying the workspace-threatens the organization's ability to continue operations. Business continuity plans address how to maintain or restore critica

Question

Midway through a project, the building the team works in is destroyed by a hurricane. Which of the following types of communication is BEST in this event?

Options

  • AIncident response
  • BBusiness continuity response
  • CResource change response
  • DSchedule response

Explanation

A business continuity response is the appropriate communication type when a major disruptive event-such as a natural disaster destroying the workspace-threatens the organization's ability to continue operations. Business continuity plans address how to maintain or restore critical functions after a catastrophic event, including relocating staff, restoring systems, and resuming project work. Incident response (A) typically refers to IT security events (e.g., data breaches). Resource change response (C) addresses personnel or equipment changes under normal conditions. Schedule response (D) handles timeline adjustments-neither captures the scale or nature of a disaster recovery situation.