Which of the following is the MOST important component against which the project manager can analyze project performance?
The correct answer is B. Project baselines. The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you'll use to monitor and compare performance measurements against. Typically you'll establish performance metrics when developing the plan and then measure…
Question
Which of the following is the MOST important component against which the project manager can analyze project performance?
Options
- ABurn rate
- BProject baselines
- CKPIs
- DBudget
How the community answered
(30 responses)- A3% (1)
- B93% (28)
- C3% (1)
Explanation
The project management plan contains the project management baseline data (typically cost, schedule, and scope), which you'll use to monitor and compare performance measurements against. Typically you'll establish performance metrics when developing the plan and then measure them once the work of the project has started.