PK0-004 · Question #418
Which of the following are MOST likely the responsibilities of the PMO? (Choose two.)
The correct answer is B. Provide governance E. Identify key performance indicators. The project management office (PMO) provides project management governance (including standards and practices) and ensures that resources, methods, tools, and techniques are shared or coordinated across all projects. The PMO sets deliverables, key performance indicators, and…
Question
Which of the following are MOST likely the responsibilities of the PMO? (Choose two.)
Options
- ASteer the project
- BProvide governance
- CJustify the business case
- DProcure hardware
- EIdentify key performance indicators
- FAct as an approval authority
How the community answered
(34 responses)- B85% (29)
- C6% (2)
- D3% (1)
- F6% (2)
Explanation
The project management office (PMO) provides project management governance (including standards and practices) and ensures that resources, methods, tools, and techniques are shared or coordinated across all projects. The PMO sets deliverables, key performance indicators, and other project parameters. It also outlines the consequences of non-performance and provides standard documentation and templates.