A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types…
The correct answer is A. Functional. A functional organization structure the project manager doesn't have authority over the resources, so situations like this can occur in a functional organization.
Project management concepts
Question
A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?
Options
- AFunctional
- BProjectized
- CStrong matrix
- DFlat
How the community answered
(17 responses)- A76% (13)
- B6% (1)
- C6% (1)
- D12% (2)
Explanation
A functional organization structure the project manager doesn't have authority over the resources, so situations like this can occur in a functional organization.
Topics
#functional organization#organizational structure#resource management#critical path