nerdexam
CompTIA

PK0-004 · Question #413

A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types…

The correct answer is A. Functional. A functional organization structure the project manager doesn't have authority over the resources, so situations like this can occur in a functional organization.

Project management concepts

Question

A task on the critical path has just been completed. The project manager has been informed that the person responsible for the next task has gone on an approved leave. Which of the following types of organizational structure does this scenario BEST describe?

Options

  • AFunctional
  • BProjectized
  • CStrong matrix
  • DFlat

How the community answered

(17 responses)
  • A
    76% (13)
  • B
    6% (1)
  • C
    6% (1)
  • D
    12% (2)

Explanation

A functional organization structure the project manager doesn't have authority over the resources, so situations like this can occur in a functional organization.

Topics

#functional organization#organizational structure#resource management#critical path

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice