PK0-004 · Question #412

A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which…

The correct answer is C. Add the new feature to the next sprint and move the old feature to the following sprint. The key word here is 'iterative release,' which signals an Agile/Scrum context. In Scrum, work is organized into sprints. When a customer requests a feature swap between releases, the correct action is to place the new feature in the next sprint and move the deferred feature to…

Project management concepts

Question

A customer has requested a new feature be included in the next iterative release. The customer has agreed to move a previously planned feature to a subsequent release and increase the budget. Which of the following is the MOST appropriate scheduling action?

Options

  • AAnalyze the critical path and update the WBS with the new feature
  • BAdd the new feature and reprioritize the product backlog
  • CAdd the new feature to the next sprint and move the old feature to the following sprint
  • DConduct a retrospective with the team to discuss the change and introduce the feature

How the community answered

(44 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    82% (36)
  • D
    11% (5)

Explanation

The key word here is 'iterative release,' which signals an Agile/Scrum context. In Scrum, work is organized into sprints. When a customer requests a feature swap between releases, the correct action is to place the new feature in the next sprint and move the deferred feature to a future sprint. Option A (critical path/WBS) is a predictive/waterfall technique, not iterative. Option B (reprioritizing the product backlog) is partially correct but incomplete - the backlog update follows naturally, and the specific sprint-level action is adding to the next sprint. Option D (retrospective) is the wrong ceremony - retrospectives are for process improvement, not for introducing scope changes.

Topics

#agile sprints#backlog management#iterative release#scope change