nerdexam
ExamsPK0-004Questions#30
CompTIA

PK0-004 · Question #30

PK0-004 Question #30: Real Exam Question with Answer & Explanation

The correct answer is B: Scope creep. A project manager refusing an informal change request during delivery is most likely preventing scope creep, which occurs when unapproved additions expand the project beyond its agreed baseline.

Question

A customer asks a project manager if a small change can be made during the delivery phase. The project manager does not agree to the change. Which of the following is the MOST likely reason?

Options

  • AEstablished communication plan
  • BScope creep
  • CResource constraints
  • DIterative approach

Explanation

A project manager refusing an informal change request during delivery is most likely preventing scope creep, which occurs when unapproved additions expand the project beyond its agreed baseline.

Common mistakes.

  • A. A communication plan governs how and when information is shared among stakeholders and is not a mechanism for refusing a change request.
  • C. Resource constraints might influence whether a change could be accommodated, but they are not the primary or most likely reason a PM refuses an unplanned in-flight change.
  • D. An iterative approach is a delivery methodology that embraces change through defined iteration cycles, making it more likely to support change requests rather than refuse them.

Concept tested. Scope creep prevention and change control process

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice