PK0-004 · Question #297

Which of the following are components in the communications management planning process?

The correct answer is D. Communications planning, information distribution, performance reporting, manage stakeholders. Communications management in PMBOK includes four processes: communications planning, information distribution, performance reporting, and manage stakeholders.

Project management concepts

Question

Which of the following are components in the communications management planning process?

Options

  • ACommunications planning, information distribution, performance reporting, project implementation
  • BCommunications planning, information distribution, performance reporting, closing
  • CCommunications planning, information distribution, performance reporting, initiating
  • DCommunications planning, information distribution, performance reporting, manage stakeholders

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    5% (1)
  • D
    91% (20)

Why each option

Communications management in PMBOK includes four processes: communications planning, information distribution, performance reporting, and manage stakeholders.

ACommunications planning, information distribution, performance reporting, project implementation

Project implementation is not a recognized process within the Communications Management knowledge area; it is an informal term sometimes used for the Executing process group.

BCommunications planning, information distribution, performance reporting, closing

Closing is a process group, not a component of the Communications Management knowledge area.

CCommunications planning, information distribution, performance reporting, initiating

Initiating is a process group, not a component of the Communications Management knowledge area.

DCommunications planning, information distribution, performance reporting, manage stakeholdersCorrect

According to the PMBOK Guide, the Communications Management knowledge area consists of exactly four processes: Communications Planning, Information Distribution, Performance Reporting, and Manage Stakeholders. These four processes collectively cover how project information is created, distributed, and managed from planning through closure.

Concept tested: PMBOK Communications Management knowledge area processes

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#communications management#stakeholder management#performance reporting#information distribution