PK0-004 · Question #268

Which of the following actions can be used to ensure the quality of project deliverables?

The correct answer is A. Analyzing performance information. Analyzing performance information is the primary quality management action used to ensure deliverables meet standards by identifying variances and measuring results against the quality baseline.

Project management concepts

Question

Which of the following actions can be used to ensure the quality of project deliverables?

Options

  • AAnalyzing performance information
  • BEnsuring all vendors are ISO certified
  • CUpdating the risk register
  • DA concise statement of work

How the community answered

(52 responses)
  • A
    94% (49)
  • C
    2% (1)
  • D
    4% (2)

Why each option

Analyzing performance information is the primary quality management action used to ensure deliverables meet standards by identifying variances and measuring results against the quality baseline.

AAnalyzing performance informationCorrect

Analyzing performance information is a core quality control and quality assurance activity that involves reviewing metrics, test results, and inspection data to verify that project deliverables conform to defined quality standards. This process identifies deviations from the quality baseline and triggers corrective actions when needed. It directly supports quality assurance by providing objective evidence that deliverables meet acceptance criteria.

BEnsuring all vendors are ISO certified

Requiring all vendors to be ISO certified is an extreme and often impractical procurement constraint that is not a standard quality assurance technique for project deliverables.

CUpdating the risk register

Updating the risk register is a risk management activity used to track and respond to project risks, not a mechanism for verifying or ensuring the quality of deliverables.

DA concise statement of work

A statement of work defines scope and requirements for procurement but does not itself constitute an action that ensures the quality of deliverables produced during the project.

Concept tested: Quality control through performance information analysis

Source: https://www.pmi.org/learning/library/quality-management-improve-project-deliverables-8218

Topics

#quality assurance#performance analysis#project deliverables#quality management