PK0-004 · Question #257

A software development project is nearing completion when a stakeholder requests additional functionality that would greatly improve the user experience with the product. Which of the following is…

The correct answer is D. Document the request. When a stakeholder requests a change, the project manager must document the request first before taking any other action, as all change control processes begin with formal documentation.

Project management concepts

Question

A software development project is nearing completion when a stakeholder requests additional functionality that would greatly improve the user experience with the product. Which of the following is the FIRST thing the project manager should do?

Options

  • AConsult the sponsor for direction
  • BInform the stakeholder that this functionality is out of scope
  • CIdentify secondary risks
  • DDocument the request

How the community answered

(31 responses)
  • A
    13% (4)
  • B
    3% (1)
  • C
    3% (1)
  • D
    81% (25)

Why each option

When a stakeholder requests a change, the project manager must document the request first before taking any other action, as all change control processes begin with formal documentation.

AConsult the sponsor for direction

Consulting the sponsor is premature before the request has been formally documented and assessed for impact.

BInform the stakeholder that this functionality is out of scope

Informing the stakeholder the request is out of scope assumes a conclusion before the change control process has evaluated it.

CIdentify secondary risks

Identifying secondary risks is a later step in change analysis, not the first action to take when a request is received.

DDocument the requestCorrect

Documenting the change request is the mandatory first step in integrated change control. Without a formal written record, the request cannot be evaluated, prioritized, or routed through the proper approval process. All subsequent actions - consulting the sponsor, assessing impact, or communicating decisions - depend on having a documented request as the input.

Concept tested: Integrated change control process initiation

Source: https://www.pmi.org/learning/library/change-control-integrated-change-management-8077

Topics

#change request#scope creep#stakeholder request#change management