PK0-004 · Question #171

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

The correct answer is C. Crash the schedule. When budget is not a constraint and schedule must be compressed, crashing the schedule by adding resources is the correct approach.

Project management concepts

Question

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

Options

  • AFast-track the tasks.
  • BUtilize positive float.
  • CCrash the schedule.
  • DRemove the critical path

How the community answered

(54 responses)
  • A
    6% (3)
  • B
    2% (1)
  • C
    81% (44)
  • D
    11% (6)

Why each option

When budget is not a constraint and schedule must be compressed, crashing the schedule by adding resources is the correct approach.

AFast-track the tasks.

Fast-tracking overlaps tasks that are normally done sequentially, reducing schedule duration without additional cost - it is the preferred method when budget is constrained, not when budget is irrelevant.

BUtilize positive float.

Positive float refers to the slack time available on non-critical tasks before they affect the project end date, and it cannot be applied to compress critical path task durations.

CCrash the schedule.Correct

Crashing the schedule involves adding resources - such as additional personnel, overtime, or equipment - to critical path tasks to shorten their duration. Since budget is not a concern in this scenario, the project manager can absorb the added cost. This is a recognized schedule compression technique specifically suited for situations where spending more money to save time is acceptable.

DRemove the critical path

The critical path cannot be removed; it is the longest sequence of dependent tasks that defines the minimum project duration and always exists in any network schedule.

Concept tested: Schedule compression - crashing vs fast-tracking trade-offs

Source: https://www.pmi.org/learning/library/schedule-compression-crashing-fast-tracking-7022

Topics

#schedule compression#crashing#critical path#resource allocation