nerdexam
ExamsPK0-004Questions#171
CompTIA

PK0-004 · Question #171

PK0-004 Question #171: Real Exam Question with Answer & Explanation

The correct answer is C: Crash the schedule.. When budget is not a constraint and schedule must be compressed, crashing the schedule by adding resources is the correct approach.

Question

A project manager does not have enough time to complete several tasks on a critical path. The budget is a low concern. Which of the following should be used to complete the tasks on time?

Options

  • AFast-track the tasks.
  • BUtilize positive float.
  • CCrash the schedule.
  • DRemove the critical path

Explanation

When budget is not a constraint and schedule must be compressed, crashing the schedule by adding resources is the correct approach.

Common mistakes.

  • A. Fast-tracking overlaps tasks that are normally done sequentially, reducing schedule duration without additional cost - it is the preferred method when budget is constrained, not when budget is irrelevant.
  • B. Positive float refers to the slack time available on non-critical tasks before they affect the project end date, and it cannot be applied to compress critical path task durations.
  • D. The critical path cannot be removed; it is the longest sequence of dependent tasks that defines the minimum project duration and always exists in any network schedule.

Concept tested. Schedule compression - crashing vs fast-tracking trade-offs

Reference. https://www.pmi.org/learning/library/schedule-compression-crashing-fast-tracking-7022

Community Discussion

No community discussion yet for this question.

Full PK0-004 Practice