While creating a project management plan, the project manager aims to reduce uncertainty about when team members will be offboarded so they can coordinate their next job assignments outside of the…

The correct answer is B. Projectized. In a projectized organizational structure, team members are assigned full-time to a project and are released (offboarded) when the project ends. This gives team members clear visibility into when they will be finished, allowing them to plan their next assignments. In a…

Project management concepts

Question

While creating a project management plan, the project manager aims to reduce uncertainty about when team members will be offboarded so they can coordinate their next job assignments outside of the organization. Which of the following organizational structures BEST represents this scenario?

Options

  • AWeak matrix
  • BProjectized
  • CStrong matrix
  • DFunctional

How the community answered

(45 responses)
  • A
    7% (3)
  • B
    76% (34)
  • C
    4% (2)
  • D
    13% (6)

Explanation

In a projectized organizational structure, team members are assigned full-time to a project and are released (offboarded) when the project ends. This gives team members clear visibility into when they will be finished, allowing them to plan their next assignments. In a functional structure (D), employees return to their department. In weak (A) and strong (C) matrix structures, employees are shared between the project and functional departments, creating ambiguity about end dates. The projectized structure best matches the scenario of clear offboarding timelines.

Topics

#organizational structure#projectized#resource offboarding#team management