Question
A project manager has contracted with a landscaping service to complete the grounds work on a new building. The landscaper provides the project manager with the following costestimate: $150 per hour, estimated time to completion=40 hours The landscaper has completed 35 hours of work. Which of the following is the Earned Value of this portion of the project?
Options
- A$750
- B$3000
- C$5250
- D$6000