Which of the following is an appropriate risk response for diverting a portion of the project risk?

The correct answer is B. Sharing. This question asks for a risk response strategy that involves distributing a part of the project risk to another party.

Project management concepts

Question

Which of the following is an appropriate risk response for diverting a portion of the project risk?

Options

  • AAvoiding
  • BSharing
  • CEnhancing
  • DExploiting

How the community answered

(55 responses)
  • A
    2% (1)
  • B
    91% (50)
  • C
    5% (3)
  • D
    2% (1)

Why each option

This question asks for a risk response strategy that involves distributing a part of the project risk to another party.

AAvoiding

Avoiding risk involves eliminating the threat entirely by changing the project plan or scope, not just diverting a portion.

BSharingCorrect

Sharing risk involves allocating ownership of the risk, or a portion of it, to another party, often through contracts, insurance, or partnerships. This strategy directly aligns with diverting a portion of the risk to reduce its impact or likelihood on the original project by involving others.

CEnhancing

Enhancing is a response strategy for opportunities (positive risks), not for diverting negative project risks.

DExploiting

Exploiting is a response strategy for opportunities (positive risks), aiming to ensure the opportunity occurs, not for diverting negative project risks.

Concept tested: Project risk response strategies - sharing

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/risk-management

Topics

#Risk response strategies#Risk sharing#Risk management