PK0-003 · Question #184
An unexpected risk has been identified in a project. Which of the following actions should the project manager perform FIRST?
The correct answer is A. Add the risk to the risk register. This question asks for the initial action a project manager should take upon identifying a new, unexpected risk.
Question
An unexpected risk has been identified in a project. Which of the following actions should the project manager perform FIRST?
Options
- AAdd the risk to the risk register
- BUpdate the project probability / impact matrix
- CSubmit a change request
- DPerform a risk qualitative analysis
How the community answered
(55 responses)- A84% (46)
- B5% (3)
- C2% (1)
- D9% (5)
Why each option
This question asks for the initial action a project manager should take upon identifying a new, unexpected risk.
The first essential step when an unexpected risk is identified is to formally document it by adding it to the risk register. This ensures the risk is officially recorded and becomes part of the project's ongoing risk management process before any further analysis or response planning can occur.
Updating the probability / impact matrix is part of qualitative risk analysis, which occurs after a risk has been identified and documented.
Submitting a change request might be necessary later if a risk response impacts the project baseline, but it is not the immediate first action upon initial risk identification.
Performing a risk qualitative analysis is a subsequent step in risk management, conducted after the risk has been identified and recorded in the risk register.
Concept tested: Risk identification and documentation process
Source: https://www.pmi.org/pmbok-guide-standards/lexicon/risk-register