A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The project manager implements the functionality while waiting for approval. This is known as which of the following?

Options

  • AChange request
  • BRisk
  • CResource constraint
  • DScope creep

Unlock PK0-003 to see the answer

You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.

Full PK0-003 Practice
A project starts out as a small three month project. One month... | PK0-003 Q#173 Answer | NerdExam