CompTIA
PK0-003 · Question #173
PK0-003 Question #173: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-003 to reveal the answer and full explanation for question #173. The question stem and answer options stay visible for context.
Question
A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The project manager implements the functionality while waiting for approval. This is known as which of the following?
Options
- AChange request
- BRisk
- CResource constraint
- DScope creep
Unlock PK0-003 to see the answer
You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.