Question
A key stakeholder changed the specifications and the testing criteria for the product. The finished product was defective and unacceptable to the customer. A post-mortem analysis is performed to:
Options
- Aassess responsibility for the failure of the project.
- Bdocument the reasons for the failure of the project.
- Caccept the cost figures from the project.
- Drelease the resources associated with the project.