nerdexam
CompTIA

PK0-003 · Question #146

A key stakeholder changed the specifications and the testing criteria for the product. The finished product was defective and unacceptable to the customer. A post-mortem analysis is performed to:

The correct answer is B. document the reasons for the failure of the project.. A post-mortem analysis is a structured review performed after a project's completion or failure to identify and document the underlying causes.

Project life cycle phases

Question

A key stakeholder changed the specifications and the testing criteria for the product. The finished product was defective and unacceptable to the customer. A post-mortem analysis is performed to:

Options

  • Aassess responsibility for the failure of the project.
  • Bdocument the reasons for the failure of the project.
  • Caccept the cost figures from the project.
  • Drelease the resources associated with the project.

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    92% (33)
  • C
    6% (2)

Why each option

A post-mortem analysis is a structured review performed after a project's completion or failure to identify and document the underlying causes.

Aassess responsibility for the failure of the project.

While a post-mortem might indirectly reveal who was involved, its primary goal is learning and process improvement, not assigning blame or assessing responsibility for individual failure.

Bdocument the reasons for the failure of the project.Correct

The primary purpose of a post-mortem analysis (also known as a lessons learned session) is to methodically identify and document the reasons for the project's failure, focusing on what went wrong and what could be done differently in the future.

Caccept the cost figures from the project.

Accepting cost figures is a financial closure activity related to project accounting and reconciliation, distinct from the analytical purpose of a post-mortem.

Drelease the resources associated with the project.

Releasing resources is an administrative project closure task, involving disbanding the project team and reassigning personnel, which is separate from a post-mortem's investigative role.

Concept tested: Purpose of post-mortem analysis

Topics

#post-mortem analysis#lessons learned#project closure

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice