nerdexam
CompTIA

PK0-003 · Question #140

As a project nears completion, the project manager finds out that several key members of the project team have been reassigned to other projects. If the scope and schedule of the project stay the same

The correct answer is A. Cost. If key team members are reassigned but the project scope and schedule remain unchanged, the project's cost will likely increase to compensate for the loss of expertise and manpower. This usually involves hiring new resources, overtime for remaining staff, or bringing in more expe

Project management concepts

Question

As a project nears completion, the project manager finds out that several key members of the project team have been reassigned to other projects. If the scope and schedule of the project stay the same which of the following will change?

Options

  • ACost
  • BQuality metrics
  • CKey Performance Indicators (KPIs)
  • DWork performance

How the community answered

(53 responses)
  • A
    83% (44)
  • B
    2% (1)
  • C
    9% (5)
  • D
    6% (3)

Why each option

If key team members are reassigned but the project scope and schedule remain unchanged, the project's cost will likely increase to compensate for the loss of expertise and manpower. This usually involves hiring new resources, overtime for remaining staff, or bringing in more expensive contractors.

ACostCorrect

If key team members are reassigned and the project's scope and schedule remain fixed, the project's cost will almost certainly change, most likely increasing. This is because the project manager will need to either replace the departed members, potentially with more expensive temporary staff or contractors, or pay overtime to the remaining team members to maintain the original schedule and scope.

BQuality metrics

While quality could be affected, quality metrics themselves are measures; the question asks what will change, and cost is a more direct and certain impact if scope and schedule are fixed and resources are lost.

CKey Performance Indicators (KPIs)

Key Performance Indicators (KPIs) are measures of performance; while performance might be impacted, the KPIs themselves do not change, but the project's ability to meet them might.

DWork performance

Work performance refers to how well the team is executing tasks; while it might be negatively impacted, "cost" is a more fundamental and directly quantifiable change when resources are removed but output requirements remain.

Concept tested: Project constraints and resource management impact

Topics

#Project constraints#Cost management#Resource management#Triple constraint

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice