You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program yo
The correct answer is D. Certificate of program completion. A Certificate of Program Completion is the formal, official document that signifies the program has officially ended and all deliverables have been accepted. It serves as the authorized closure artifact for the program. Lessons learned documentation (C), a final audit report (A),
Question
You are the program manager for your organization. You are planning a new program that will construct a new warehouse facility for your company. As you look forward to the conclusion of the program you need an official document that will signify the program has ended. What document should you specify in your program management plan for the conclusion of the program?
Options
- AFinal program audit report
- BAudit of program financials
- CLessons learned documentation
- DCertificate of program completion
How the community answered
(19 responses)- B5% (1)
- D95% (18)
Explanation
A Certificate of Program Completion is the formal, official document that signifies the program has officially ended and all deliverables have been accepted. It serves as the authorized closure artifact for the program. Lessons learned documentation (C), a final audit report (A), and an audit of financials (B) are all valuable program closure activities, but none of them serve as the official document that formally declares the program complete and closed.