PGMP · Question #90

You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of…

The correct answer is A. How quality control will be included in the scope. The Program Scope Management Plan defines how the scope will be created (C), how changes to scope will be managed and allowed (B), and how scope will be controlled and monitored (D). It does NOT define how quality control will be incorporated - that is the responsibility of the…

Program Scope Management

Question

You are the program manager for your organization and are working with your team to create the program scope management plan. This plan defines several things in your program except for which one of the following?

Options

  • AHow quality control will be included in the scope
  • BHow changes may be allowed to enter the program scope
  • CHow the program scope will be created for your program
  • DHow the program scope will be controlled

How the community answered

(35 responses)
  • A
    94% (33)
  • C
    3% (1)
  • D
    3% (1)

Explanation

The Program Scope Management Plan defines how the scope will be created (C), how changes to scope will be managed and allowed (B), and how scope will be controlled and monitored (D). It does NOT define how quality control will be incorporated - that is the responsibility of the Quality Management Plan. Quality and scope are separate knowledge areas in program management. Including quality control processes in the scope management plan would be a category error; therefore, option A is the one item NOT covered by this plan.

Topics

#Program Scope Management#Scope Management Plan#Program Planning#Management Plans

Community Discussion

No community discussion yet for this question.