PGMP · Question #84

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each…

The correct answer is C. Stakeholder analysis chart. A Stakeholder Analysis Chart is specifically designed to capture detailed information about each stakeholder, including their opinions, influence, requirements, interest levels, and effect on program priorities. A Resource Breakdown Structure (A) categorizes resources by type…

Stakeholder Engagement

Question

Gary is the program manager for his organization. His current program has 432 stakeholders, some of which are external to his organization. He would like to create a chart that identifies each stakeholder's opinion of the program, influence over program decisions, their requirements and affect on program priorities, and other information. What kind of chart should Gary create in this instance?

Options

  • AResource breakdown structure
  • BResource management chart
  • CStakeholder analysis chart
  • DRACI chart

How the community answered

(35 responses)
  • A
    9% (3)
  • B
    3% (1)
  • C
    86% (30)
  • D
    3% (1)

Explanation

A Stakeholder Analysis Chart is specifically designed to capture detailed information about each stakeholder, including their opinions, influence, requirements, interest levels, and effect on program priorities. A Resource Breakdown Structure (A) categorizes resources by type. A RACI chart (D) documents responsibility assignments (Responsible, Accountable, Consulted, Informed) for tasks. A Resource Management Chart (B) is not a standard program management artifact. Only the stakeholder analysis chart fits all the criteria Gary needs.

Topics

#Stakeholder Management#Stakeholder Analysis#Program Management Tools#Stakeholder Register