PGMP · Question #74

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the…

The correct answer is A. Change requests. Change requests (Choice A) are an OUTPUT of schedule control, not an input or tool that helps you perform it. When you conduct schedule control activities, you may discover variances that lead you to generate change requests - but the change requests themselves don't help you…

Program Life Cycle Management

Question

You are the program manager for the JQN Program in your organization. There have been some delays in your schedule and you're about to perform some schedule control activities. Which one of the following will not help you as you perform schedule control?

Options

  • AChange requests
  • BPerformance reports
  • CForecasts
  • DEarned value management

How the community answered

(35 responses)
  • A
    74% (26)
  • B
    14% (5)
  • C
    3% (1)
  • D
    9% (3)

Explanation

Change requests (Choice A) are an OUTPUT of schedule control, not an input or tool that helps you perform it. When you conduct schedule control activities, you may discover variances that lead you to generate change requests - but the change requests themselves don't help you perform the control process. Performance reports, forecasts, and earned value management are all inputs or techniques that directly support schedule control: performance reports show actual vs. planned progress, forecasts estimate future performance, and earned value management quantifies schedule variance and performance indexes.

Topics

#Schedule Control#Program Schedule Management#Change Requests#Earned Value Management