PGMP · Question #6
PGMP Question #6: Real Exam Question with Answer & Explanation
Sign in or unlock PGMP to reveal the answer and full explanation for question #6. The question stem and answer options stay visible for context.
Question
You are the program manager for your organization. Management has asked you to create a method to track the program stakeholders' concerns, threats, and demands for communication. They would like you to map out each stakeholder or stakeholder group and identify trends within the chart to help your program communicate better. What type of a chart should you create for management?
Options
- ARACI chart
- BStakeholder analysis chart
- CRoles and responsibilities chart
- DCommunication matrix