Question
Your program has a budget at completion of $1,550,000 and is expected to last one year. Currently your program is 45 percent complete and has spent $725,000. According to the program schedule you are actually to be fifty percent complete by this time, but due to some vendor delays your program is running just a bit late. Based on this information which is performing worse, the cost or schedule?
Options
- AThe schedule is performing worse because the SPI is .90
- BThe cost is performing worse because the EAC is $1,611,111.
- CThe schedule is performing worse because the SV is -$27,500.
- DThe cost is performing worse because the CPI is .96.