The correct answer is B: Enterprise environmental factors. See the full explanation below for the reasoning.

Program Governance

Question

You are the program manager for your organization. Your program has recently completed its program scope and you've transferred the benefits to the operations of your organization. Before your program is considered closed you must complete some forms and procedures as required by your organization. The requirements to complete the forms and paperwork are also known as what?

Options

  • AProgram administrative closure
  • BEnterprise environmental factors
  • CClosing processes
  • DOrganizational process assets

Topics

#Enterprise Environmental Factors#Program Closure#Organizational Policy#Program Governance

Community Discussion