nerdexam
PMI

PGMP · Question #572

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

The correct answer is B. Gather all the details, analyze impacts, determine corrective actions and present the findings to the. When a negative cost variance triggers a red flag, the program manager must follow a structured response process before escalating to any stakeholders or sponsors. Option B reflects the correct sequence: (1) gather all details, (2) analyze the impacts, (3) determine corrective ac

Program Life Cycle Management

Question

The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?

Options

  • AContact the project sponsors to present the details, impacts, and possible corrective actions
  • BGather all the details, analyze impacts, determine corrective actions and present the findings to the
  • CWork with program sponsor to compile impact analysis data to obtain additional funding for the
  • DAsk the program team to compile all details, analyze impacts, determine corrective actions and

How the community answered

(40 responses)
  • A
    23% (9)
  • B
    63% (25)
  • C
    10% (4)
  • D
    5% (2)

Explanation

When a negative cost variance triggers a red flag, the program manager must follow a structured response process before escalating to any stakeholders or sponsors. Option B reflects the correct sequence: (1) gather all details, (2) analyze the impacts, (3) determine corrective actions, and then (4) present findings. Option A skips the analysis and corrective action phases, arriving at sponsors unprepared. Option C jumps directly to seeking additional funding without first doing the analysis - funding may not even be the right corrective action. Option D delegates the entire process to the team, which is an abdication of the program manager's accountability. The program manager owns the analysis and the recommendation before any presentation occurs.

Topics

#Cost Variance#Program Control#Corrective Action#Issue Management

Community Discussion

No community discussion yet for this question.

Full PGMP Practice