PGMP · Question #573
After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder…
The correct answer is C. Inform the stakeholder that the program will not be changed until proof of concept (PoC) is. An influential stakeholder requesting immediate integration of unproven technology poses significant program risk. The correct first response is to inform the stakeholder that a Proof of Concept (PoC) must be completed before any integration commitment is made. This protects…
Question
After attending a technology exposition, an influential stakeholder believes that integrating a new technology into the program will increase benefits and help shorten the schedule. The stakeholder asks the program manager to immediately include the new technology into the program. What should the program manager do next?
Options
- AAssess the new technology and discuss the results with the program steering committee to
- BStart the change management process and submit a change request to integrate the new
- CInform the stakeholder that the program will not be changed until proof of concept (PoC) is
- DResearch the new technology and begin its integration during the next development cycle.
How the community answered
(32 responses)- A6% (2)
- B6% (2)
- C72% (23)
- D16% (5)
Explanation
An influential stakeholder requesting immediate integration of unproven technology poses significant program risk. The correct first response is to inform the stakeholder that a Proof of Concept (PoC) must be completed before any integration commitment is made. This protects the program from schedule and scope risk tied to untested technology. Option A involves the steering committee but implies the technology might be integrated based solely on an assessment, bypassing PoC validation. Option B starts the change management process prematurely - before the technology is even validated. Option D begins integration without governance approval or validation, which is reckless. PoC is the required gate before any change request or integration can proceed.
Topics
Community Discussion
No community discussion yet for this question.