nerdexam
PMI

PGMP · Question #558

A program manager joins a team during its preparation phase. What should the program manager do to obtain formal sponsor approval to begin the benefits delivery phase?

The correct answer is C. Define a high-level program roadmap of milestones and schedules supported by a preliminary. To transition from the preparation phase to the benefits delivery phase, the program manager must demonstrate to the sponsor that the program is ready to proceed. A high-level program roadmap - showing milestones, schedules, and supported by preliminary estimates - gives the…

Program Life Cycle Management

Question

A program manager joins a team during its preparation phase. What should the program manager do to obtain formal sponsor approval to begin the benefits delivery phase?

Options

  • ADevelop the program management plan based on the organization's strategic plan.
  • BWrite the program charter, including the program mission statement and stakeholder engagement
  • CDefine a high-level program roadmap of milestones and schedules supported by a preliminary
  • DIdentify and document the anticipated program benefits in the benefits management plan.

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    12% (5)
  • C
    80% (33)
  • D
    5% (2)

Explanation

To transition from the preparation phase to the benefits delivery phase, the program manager must demonstrate to the sponsor that the program is ready to proceed. A high-level program roadmap - showing milestones, schedules, and supported by preliminary estimates - gives the sponsor the clarity and confidence needed to grant formal approval. The roadmap directly answers 'when will benefits be delivered and how?' Option A (developing the full program management plan) is too broad for the preparation phase. Option B (writing the charter) should already be done. Option D (documenting anticipated benefits) is important but insufficient on its own to demonstrate readiness for execution.

Topics

#Program Life Cycle#Phase Gates#Sponsor Approval#Program Planning

Community Discussion

No community discussion yet for this question.

Full PGMP Practice