PGMP · Question #535
A program has been established and preparation is complete. Component projects are planned as a part of which of the following?
The correct answer is B. Program formulation. In PMI's Standard for Program Management, Program Formulation is the sub-phase within the Program Definition phase where the program's structure is established, including the identification and initial planning of component projects. This is when the program's scope, objectives,
Question
A program has been established and preparation is complete. Component projects are planned as a part of which of the following?
Options
- AProgram definition phase
- BProgram formulation
- CProgram planning
- DProgram delivery phase
How the community answered
(25 responses)- B92% (23)
- C4% (1)
- D4% (1)
Explanation
In PMI's Standard for Program Management, Program Formulation is the sub-phase within the Program Definition phase where the program's structure is established, including the identification and initial planning of component projects. This is when the program's scope, objectives, and component breakdown are formalized. Program Planning (C) is a separate sub-phase that follows formulation and focuses on detailed plans at the program level. The Program Delivery Phase (D) is when components are executed, not planned. Program Definition Phase (A) is the broader parent phase that encompasses both formulation and planning.