PGMP · Question #420
What actions are taken in the process of developing and maintaining a program risk register?
The correct answer is C. Assign ownership of risks with appropriate responsibilities, document agreed-upon response. Note: In this question, the answer choices appear identical in the provided text due to truncation. The correct answer (C) reflects the complete set of actions involved in developing and maintaining a program risk register. These actions include: identifying and documenting…
Question
What actions are taken in the process of developing and maintaining a program risk register?
Options
- AAssign ownership of risks with appropriate responsibilities, document agreed-upon response
- BAssign ownership of risks with appropriate responsibilities, document agreed-upon response
- CAssign ownership of risks with appropriate responsibilities, document agreed-upon response
- DAssign ownership of risks with appropriate responsibilities, document agreed-upon response
How the community answered
(24 responses)- A8% (2)
- B4% (1)
- C88% (21)
Explanation
Note: In this question, the answer choices appear identical in the provided text due to truncation. The correct answer (C) reflects the complete set of actions involved in developing and maintaining a program risk register. These actions include: identifying and documenting risks with unique identifiers; assigning ownership to individuals with appropriate authority and accountability; documenting agreed-upon response strategies (avoid, transfer, mitigate, accept); establishing probability and impact ratings; and regularly updating the register throughout the program lifecycle as new risks emerge and existing ones are resolved. The risk register is a living document, and its value depends on continuous maintenance and clear ownership of each risk item.
Topics
Community Discussion
No community discussion yet for this question.