PMIPMI
PGMP · Question #404
PGMP Question #404: Real Exam Question with Answer & Explanation
Sign in or unlock PGMP to reveal the answer and full explanation for question #404. The question stem and answer options stay visible for context.
Program Life Cycle Management
Question
A program is completed and the expected benefits are realized. Before executing the transition and closing of the program, what should the program manager do?
Options
- ACreate a final program report
- BArchive documents and lessons learned
- CObtain approval from the program governance board to initiate program closure activities
- DPerform administrative and program management information system (PMIS) closure
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Program Closure#Archiving#Lessons Learned#Program Lifecycle