Program Life Cycle Management
Question
You are the Project Manager for a national satellite rollout project. You are required to purchase and integrate reporting software for all the retail stores. As the Project Manager, you want one price from the vendors for the purchase and implementation of this product. What type of document should be used?
Options
- AInvitation for bid
- BRequest for quote
- CRequest for proposal
- DRequest for information
Unlock PGMP to see the answer
You've previewed enough free PGMP questions. Unlock PGMP for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.
Topics
#Procurement#Request for Proposal (RFP)#Source Selection#Project Documents