PGMP · Question #370
You are the Project Manager for a national satellite rollout project. You are required to purchase and integrate reporting software for all the retail stores. As the Project Manager, you want one…
The correct answer is C. Request for proposal. A Request for Proposal (RFP) is used when the buyer wants vendors to propose both their solution approach AND pricing for a complex scope of work - in this case, both the purchase AND implementation of software. An RFP invites vendors to describe how they would accomplish the…
Question
You are the Project Manager for a national satellite rollout project. You are required to purchase and integrate reporting software for all the retail stores. As the Project Manager, you want one price from the vendors for the purchase and implementation of this product. What type of document should be used?
Options
- AInvitation for bid
- BRequest for quote
- CRequest for proposal
- DRequest for information
How the community answered
(33 responses)- A15% (5)
- B9% (3)
- C73% (24)
- D3% (1)
Explanation
A Request for Proposal (RFP) is used when the buyer wants vendors to propose both their solution approach AND pricing for a complex scope of work - in this case, both the purchase AND implementation of software. An RFP invites vendors to describe how they would accomplish the work and at what cost. An Invitation for Bid (IFB) is used when requirements are fully defined and you only need the lowest price (no solution proposal needed). A Request for Quote (RFQ) is used for simpler, commodity purchases. A Request for Information (RFI) is used to gather market information, not to initiate a procurement.