nerdexam
PMIPMI

PGMP · Question #369

PGMP Question #369: Real Exam Question with Answer & Explanation

The correct answer is C: Time and materials. See the full explanation below for the reasoning.

Financial Management

Question

A project you have been managing is falling behind schedule. You have received approval to crash the project by adding an additional programmer. The cost you have negotiated is $60 US per hour. The programmer will work on the project until it is complete, then the contract will end. What type of contract is this?

Options

  • ACost-plus
  • BPurchase order
  • CTime and materials
  • DFixed-price

Topics

#Contract types#Procurement management#Time and materials contract

Community Discussion

No community discussion yet for this question.

Full PGMP PracticeBrowse All PGMP Questions