nerdexam
PMI

PGMP · Question #369

A project you have been managing is falling behind schedule. You have received approval to crash the project by adding an additional programmer. The cost you have negotiated is $60 US per hour. The…

The correct answer is C. Time and materials. Time and Materials (T&M) contracts pay the vendor based on the actual time spent (e.g., an hourly rate) plus the cost of any materials used. The key indicators here are: (1) the programmer is paid a set hourly rate ($60/hour), and (2) the contract duration is open-ended - it…

Financial Management

Question

A project you have been managing is falling behind schedule. You have received approval to crash the project by adding an additional programmer. The cost you have negotiated is $60 US per hour. The programmer will work on the project until it is complete, then the contract will end. What type of contract is this?

Options

  • ACost-plus
  • BPurchase order
  • CTime and materials
  • DFixed-price

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    79% (26)
  • D
    12% (4)

Explanation

Time and Materials (T&M) contracts pay the vendor based on the actual time spent (e.g., an hourly rate) plus the cost of any materials used. The key indicators here are: (1) the programmer is paid a set hourly rate ($60/hour), and (2) the contract duration is open-ended - it continues until the work is complete. This means the total cost is variable and depends on how many hours are actually worked. Fixed-Price would require a single agreed total price. Cost-Plus would reimburse all costs plus a fee. A Purchase Order is a unilateral document typically used for defined goods, not ongoing labor.

Topics

#Contract types#Procurement management#Time and materials contract

Community Discussion

No community discussion yet for this question.

Full PGMP Practice