Where are negative risks recorded?

The correct answer is C. Risk register. The risk register is the single repository for all identified risks - both negative risks (threats) and positive risks (opportunities). There is no such thing as a separate 'negative risk register' (A) in standard project/program management frameworks. The risk management plan…

Program Life Cycle Management

Question

Where are negative risks recorded?

Options

  • ANegative risk register
  • BRisk management plan
  • CRisk register
  • DIssues log

How the community answered

(24 responses)
  • B
    8% (2)
  • C
    88% (21)
  • D
    4% (1)

Explanation

The risk register is the single repository for all identified risks - both negative risks (threats) and positive risks (opportunities). There is no such thing as a separate 'negative risk register' (A) in standard project/program management frameworks. The risk management plan (B) describes the approach, methodology, roles, and processes for managing risk - it does not store individual risk entries. The issues log (D) captures issues that have already occurred and require resolution, not risks that might occur in the future. All identified risks, regardless of whether they are threats or opportunities, are logged in the risk register along with their probability, impact, response strategies, and owners.

Topics

#Risk Management#Risk Register#Threats#Program Documentation

Community Discussion

No community discussion yet for this question.

Full PGMP Practice