nerdexam
PMI

PGMP · Question #317

Rick is a Program Manager for a large construction program. The program contains four projects. Stakeholders have requested for some changes that will change the scope of the program. Rick needs to mo

The correct answer is A. Program scope statement. The program scope statement is the key reference document for evaluating change requests against the program's defined deliverables, acceptance criteria, and work boundaries.

Program Life Cycle Management

Question

Rick is a Program Manager for a large construction program. The program contains four projects. Stakeholders have requested for some changes that will change the scope of the program. Rick needs to monitor and control program scope. He is required to analyze the change request with detailed deliverables, acceptance criterion, and the work of the program. Which of the following documents will help him for this?

Options

  • AProgram scope statement
  • BProject charter
  • CProgram performance report
  • DProgram charter

How the community answered

(17 responses)
  • A
    71% (12)
  • B
    6% (1)
  • C
    18% (3)
  • D
    6% (1)

Why each option

The program scope statement is the key reference document for evaluating change requests against the program's defined deliverables, acceptance criteria, and work boundaries.

AProgram scope statementCorrect

The program scope statement contains the detailed description of the program's deliverables, acceptance criteria, exclusions, constraints, and assumptions - precisely the information Rick needs to analyze change requests against the agreed scope baseline. Comparing a proposed change to the program scope statement allows the program manager to determine what work is in scope and what will require a formal scope change.

BProject charter

The project charter authorizes the project at a high level and does not contain the detailed deliverables and acceptance criteria needed for change analysis.

CProgram performance report

The program performance report tracks execution metrics and progress but does not contain scope definitions or acceptance criteria for evaluating changes.

DProgram charter

The program charter authorizes the program and defines its high-level objectives but lacks the granular deliverable descriptions and acceptance criteria required for change control analysis.

Concept tested: Program scope statement use in scope change control

Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management

Topics

#Program Scope Management#Program Documentation#Change Control#Scope Baseline

Community Discussion

No community discussion yet for this question.

Full PGMP Practice