nerdexam
PMI

PGMP · Question #275

A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Onc

The correct answer is B. Defect repair validation. After a defect has been repaired, the next step is defect repair validation - formally inspecting and verifying that the repair was performed correctly and the issue has been resolved. This is a quality control activity. Lessons learned come at the end of a phase or project. Corr

Program Life Cycle Management

Question

A team member has made a mistake during the installation of a fixture in your program. You have requested that the team member should correct the problem so that the fixture is installed properly. Once the team members has corrected the problem what action should be taken next?

Options

  • ALesson learned documentation
  • BDefect repair validation
  • CCorrective actions
  • DPreventive actions

How the community answered

(42 responses)
  • A
    14% (6)
  • B
    76% (32)
  • C
    2% (1)
  • D
    7% (3)

Explanation

After a defect has been repaired, the next step is defect repair validation - formally inspecting and verifying that the repair was performed correctly and the issue has been resolved. This is a quality control activity. Lessons learned come at the end of a phase or project. Corrective actions are what triggered the repair in the first place, and preventive actions address future issues. Since the repair is already done, validation is the immediate next step.

Topics

#Quality Management#Defect Management#Program Control#Validation

Community Discussion