nerdexam
PMI

PGMP · Question #248

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

The correct answer is A. Fast tracking. Fast tracking is the schedule compression technique where two activities originally planned sequentially are performed in parallel by starting them at the same time.

Program Life Cycle Management

Question

Which of the following terms is used for a schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time?

Options

  • AFast tracking
  • BCompressing
  • CFloat
  • DCrashing

How the community answered

(29 responses)
  • A
    90% (26)
  • C
    7% (2)
  • D
    3% (1)

Why each option

Fast tracking is the schedule compression technique where two activities originally planned sequentially are performed in parallel by starting them at the same time.

AFast trackingCorrect

Fast tracking compresses the project schedule by overlapping activities that were planned to be done sequentially, effectively starting a successor activity before its predecessor is fully complete. This reduces overall duration but increases risk because the downstream activity begins before all required inputs from the upstream activity are available.

BCompressing

'Compressing' is a generic English word and not a recognized schedule compression technique in PMBOK terminology - no such named technique exists.

CFloat

Float (also called slack) is the amount of time a task can be delayed without affecting the project end date - it is a scheduling measurement, not a compression technique.

DCrashing

Crashing compresses the schedule by adding additional resources to critical path activities to shorten their duration, not by overlapping sequential activities.

Concept tested: Fast tracking schedule compression technique

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok

Topics

#Schedule Management#Schedule Compression#Fast Tracking#Project Scheduling

Community Discussion

No community discussion yet for this question.

Full PGMP Practice