PGMP · Question #222
What does CPI value less than 1.0 indicates?
The correct answer is A. Cost overrun for work completed. CPI (Cost Performance Index) = Earned Value (EV) / Actual Cost (AC). A CPI less than 1.0 means the actual cost exceeds the earned value - you are spending more money than the value of work completed, which is a cost overrun. A CPI of exactly 1.0 means cost is on track (D). A…
Question
What does CPI value less than 1.0 indicates?
Options
- ACost overrun for work completed
- BScheduled performance is great
- CCost underrun of performance to date
- DCost for completed work is as per estimate
How the community answered
(25 responses)- A88% (22)
- C8% (2)
- D4% (1)
Explanation
CPI (Cost Performance Index) = Earned Value (EV) / Actual Cost (AC). A CPI less than 1.0 means the actual cost exceeds the earned value - you are spending more money than the value of work completed, which is a cost overrun. A CPI of exactly 1.0 means cost is on track (D). A CPI greater than 1.0 indicates a cost underrun (C). CPI is a cost metric, not a schedule metric, so it has no direct bearing on schedule performance (B), which is measured by SPI (Schedule Performance Index).
Topics
Community Discussion
No community discussion yet for this question.