nerdexam
PMI

PGMP · Question #222

What does CPI value less than 1.0 indicates?

The correct answer is A. Cost overrun for work completed. CPI (Cost Performance Index) = Earned Value (EV) / Actual Cost (AC). A CPI less than 1.0 means the actual cost exceeds the earned value - you are spending more money than the value of work completed, which is a cost overrun. A CPI of exactly 1.0 means cost is on track (D). A…

Program Life Cycle Management

Question

What does CPI value less than 1.0 indicates?

Options

  • ACost overrun for work completed
  • BScheduled performance is great
  • CCost underrun of performance to date
  • DCost for completed work is as per estimate

How the community answered

(25 responses)
  • A
    88% (22)
  • C
    8% (2)
  • D
    4% (1)

Explanation

CPI (Cost Performance Index) = Earned Value (EV) / Actual Cost (AC). A CPI less than 1.0 means the actual cost exceeds the earned value - you are spending more money than the value of work completed, which is a cost overrun. A CPI of exactly 1.0 means cost is on track (D). A CPI greater than 1.0 indicates a cost underrun (C). CPI is a cost metric, not a schedule metric, so it has no direct bearing on schedule performance (B), which is measured by SPI (Schedule Performance Index).

Topics

#Earned Value Management (EVM)#Cost Performance Index (CPI)#Cost Performance#Performance Measurement

Community Discussion

No community discussion yet for this question.

Full PGMP Practice