PGMP · Question #221
You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program mana
The correct answer is B. Program closure reports. When a program reaches completion, the program manager is responsible for formally closing the program. Program closure reports are the required output at this stage - they document the program's outcomes, performance against objectives, final status of deliverables, and formally
Question
You are the program manager of the NHQ Program. The program has reached its final deliverable and the certificate of completion has been created for the program. What else should you, the program manager, create at this time?
Options
- AOperational transfer plan
- BProgram closure reports
- CLife cycle costing estimates
- DLessons learned documentation
How the community answered
(26 responses)- A4% (1)
- B88% (23)
- C8% (2)
Explanation
When a program reaches completion, the program manager is responsible for formally closing the program. Program closure reports are the required output at this stage - they document the program's outcomes, performance against objectives, final status of deliverables, and formally signal that the program is closed. While lessons learned (D) are important, they are typically an input to or component of the closure process, not a standalone deliverable created at this specific moment. An operational transfer plan (A) would have been created earlier, before final delivery. Life cycle costing estimates (C) are a planning artifact, not a closure artifact.