nerdexam
PMI

PGMP · Question #216

When is the lessons learned document updated?

The correct answer is C. Throughout the project lifecycle. Best practice per PMI and other frameworks is to capture and update lessons learned continuously throughout the entire project or program lifecycle-not just at closing. Waiting until the end risks forgetting important insights. Updating lessons learned during execution…

Program Life Cycle Management

Question

When is the lessons learned document updated?

Options

  • AAt closing phase
  • BAt planning phase
  • CThroughout the project lifecycle
  • DAt execution phase

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    3% (1)
  • C
    93% (28)

Explanation

Best practice per PMI and other frameworks is to capture and update lessons learned continuously throughout the entire project or program lifecycle-not just at closing. Waiting until the end risks forgetting important insights. Updating lessons learned during execution, monitoring, and each phase ensures timely capture of knowledge while it is fresh, and allows the current team to benefit from those lessons during the active project.

Topics

#Lessons Learned#Knowledge Management#Program Lifecycle#Continuous Improvement

Community Discussion

No community discussion yet for this question.

Full PGMP Practice