PGMP · Question #217
A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on…
The correct answer is A. .93. CPI = EV / AC. First, calculate Earned Value (EV): EV = BAC × % actually complete = $550,000 × 0.45 = $247,500. Actual Cost (AC) = $265,000 (given). CPI = $247,500 / $265,000 = 0.934 ≈ 0.93. A CPI below 1.0 means the program is over budget (getting less than $1 of value for…
Question
A program has a BAC of $550,000 and is currently 45 percent complete though was actually scheduled to be 55 percent complete by this time. The program has spent, however, $265,000 to date. Based on this information what is the cost performance index (CPI) for this program?
Options
- A.93
- B.82
- C$323,889
- D-$38,889
How the community answered
(33 responses)- A85% (28)
- B9% (3)
- C3% (1)
- D3% (1)
Explanation
CPI = EV / AC. First, calculate Earned Value (EV): EV = BAC × % actually complete = $550,000 × 0.45 = $247,500. Actual Cost (AC) = $265,000 (given). CPI = $247,500 / $265,000 = 0.934 ≈ 0.93. A CPI below 1.0 means the program is over budget (getting less than $1 of value for every $1 spent). Note: The scheduled completion percentage (55%) is used to calculate SPI (Schedule Performance Index), not CPI.
Topics
Community Discussion
No community discussion yet for this question.