PGMP · Question #259
You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison wi
The correct answer is C. Monitor and Control Project Performance. Comparing actual project completions against the planned baseline is performed within the Monitor and Control Project Performance process.
Question
You work as a program manager for a large construction program. Your program includes constructing hotels across the country. You collect information on the status of the program. During comparison with the original plan you find the 200 hotels have been completed as against 275 hotels planned as of today. In which program process are you working on?
Options
- AMonitor and Control Program Scope
- BMonitor and Control Program Schedule
- CMonitor and Control Project Performance
- DManage Program Issues
How the community answered
(60 responses)- A13% (8)
- B7% (4)
- C77% (46)
- D3% (2)
Why each option
Comparing actual project completions against the planned baseline is performed within the Monitor and Control Project Performance process.
Monitor and Control Program Scope focuses on whether the work being performed is within the defined scope boundaries, not on schedule or delivery quantity comparisons.
Monitor and Control Program Schedule focuses specifically on timeline and schedule variances, whereas the scenario describes a deliverable quantity comparison rather than a date or duration variance.
Monitor and Control Project Performance involves collecting performance data from constituent projects and comparing results against the program management plan baseline. Identifying that 200 hotels are completed versus the 275 planned is a performance variance analysis activity that falls squarely within this monitoring and controlling process, which tracks overall program delivery against planned targets.
Manage Program Issues addresses identified issues and their resolution, not performance measurement against the baseline plan.
Concept tested: Monitor and Control Project Performance process
Source: https://www.pmi.org/pmbok-guide-standards/foundational/standard-for-program-management